Tikapur Details
Tikapur
This 12-month project delivered in 11 months is the largest SCADA integrated project in the Mid-Western terai region of Nepal. The main challenge was to automatize the compressors of pressure filters, which was done efficiently by the team.
Equipment to automatize;
a.4 numbers of Pumping Management Systems with 18 pumps
b.11 numbers of Automatic Meter Readers
c.4 numbers of Outlet Management Systems
d.13 numbers of Village Transfer Chambers
e.11 numbers of Air Management Systems