Sitalpati Details
Sitalpati
This 12-month project delivered in 11 months is the largest SCADA in the Mid-Western Hilly region of Nepal. The main challenge was to operate the control valves in near 0 pressure, which was done efficiently by the team.
Equipment to automatize;
a.3 numbers of Pumping Management Systems with 9 pumps
b.10 numbers of Automatic Meter Readers
c.4 numbers of Reservoir Management Systems
d.9 numbers of Outlet Management Systems
9 numbers of Air Management Systems