This 12-month project delivered in just 7 months is the largest SCADA integrated project in the eastern Terai region of Nepal. The main challenge was to effectively operate valves in a manganese filled water, which was executed efficiently by the team.
Equipment to automatize;
a.4 numbers of Pumping Management Systems with 10 pumps
b.10 numbers of Outlet Management Systems
c.1 number of Village Transfer Chamber
d.8 numbers of Air Management Systems